This month, EB-LINK transformed the organizational method verified in the inter-building 100G upgrade project of a large data center in East China into standard delivery: cutover projects are equipped with spare parts pre-package along with the goods, and double shifts of operation and verification are adopted on site. The plan originated from two pitfalls in the project review. See the case100G optical fiber interconnection upgrade between buildings in a large data center in East China.
Spare parts kit: keep the most easily missing items at hand
At that time, on the third night of the cutover, the on-site dust caps and end-face cleaning pens were exhausted, and they were temporarily seconded to the computer room management, which was delayed for more than ten minutes. This standard spare parts package contains end-face detectors, cleaning agents, spare jumpers and adapters according to the proportions listed in the list, and is supplied with optical modules,100G DAC high speed cableShip in the same box to avoid people at the window waiting for materials on site. The quantity of each item in the spare parts package is listed, and the owner can self-check and replenish according to the list.
How to schedule double shifts
- The day shift is responsible for walk-through and pre-checking, while the night shift only performs confirmed actions;
- The operator and the checker are fixedly matched, and the checker holds the ledger and reads the numbers one by one;
- It is mandatory to change hands and rest between two windows, and those who stay up late will not be allowed to enter the next window;
- Leave a technical support person at the remote end to handle coding compatibility and module exceptions.
Write discipline into the ledger
The new organizational method was subsequently piloted in two transformation projects. The proportion of terminals completed at one time within the window was increased, and the average execution time of a single link was shorter than that of the initial project. The review believes that organizational discipline in the window must be ensured by rotation and rest, and fatigue work is the main source of misoperation. According to the review standards, similar interruptions have not occurred since the transformation went online.
The spare parts list template and rotation checklist have been released with the EB-LINK cutover project delivery package, and the project manager can request it by calling 0755-83179002.